46 CFR §56.97-25
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)Exposure of joints. All joints including welds must be left uninsulated and exposed for examination during the test.
- (b)Addition of temporary supports. Piping systems designed for vapor or gas may be provided with additional temporary supports, if necessary.
- (c)Restraint or isolation of expansion joints. Expansion joints must be provided with temporary restraint, if required for the additional pressure load under test.
- (d)Isolation of equipment not subjected to pressure test. Equipment that is not to be subjected to the pressure test must be isolated by a blank flange or equivalent means.
- (e)Treatment of flanged joints containing blinds. Flanged joints at which blinds are inserted to blank off other equipment during the test need not be tested.
- (f)Precautions against test medium expansion. If a pressure test is to be maintained for a period of time and the test medium in the system is subject to thermal expansion, precautions must be taken to avoid excessive pressure. A small relief valve set to 1 1/3 times the test pressure is recommended during the pressure test.