48 CFR §11.401
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)The time of delivery or performance is an essential contract element and shall be clearly stated in solicitations. Contracting officers shall ensure that delivery or performance schedules are realistic and meet the requirements of the acquisition. Schedules that are unnecessarily short or difficult to attain—
- (b)Solicitations shall, except when clearly unnecessary, inform bidders or offerors of the basis on which their bids or proposals will be evaluated with respect to time of delivery or performance.
- (c)If timely delivery or performance is unusually important to the Government, liquidated damages clauses may be used (see subpart 11.5).