48 CFR §19.602-2
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
Within 15 business days (or a longer period agreed to by the SBA and the contracting agency) after receiving a notice that a small business concern lacks certain elements of responsibility, the SBA Area Office will take the following actions:
- (a)Inform the small business concern of the contracting officer's determination and offer it an opportunity to apply to the SBA for a COC. (A concern wishing to apply for a COC should notify the SBA Area Office serving the geographical area in which the headquarters of the offeror is located.)
- (b)Upon timely receipt of a complete and acceptable application, elect to visit the applicant's facility to review its responsibility.
- (1)The COC review process is not limited to the areas of nonresponsibility cited by the contracting officer.
- (2)The SBA may, at its discretion, independently evaluate the COC applicant for all elements of responsibility, but may presume responsibility exists as to elements other than those cited as deficient.
- (c)Consider denying a COC for reasons of nonresponsibility not originally cited by the contracting officer.
- (d)When the Area Director determines that a COC is warranted (for contracts valued at $25,000,000 or less), notify the contracting officer and provide the following options:
- (1)Accept the Area Director's decision to issue a COC and award the contract to the concern. The COC issuance letter will then be sent, including as an attachment a detailed rationale for the decision; or
- (2)Ask the Area Director to suspend the case for one or more of the following purposes:
- (i)To permit the SBA to forward a detailed rationale for the decision to the contracting officer for review within a specified period of time.
- (ii)To afford the contracting officer the opportunity to meet with the Area Office to review all documentation contained in the case file and to attempt to resolve any issues.
- (iii)To submit any information to the SBA Area Office that the contracting officer believes the SBA did not consider (at which time the SBA Area Office will establish a new suspense date mutually agreeable to the contracting officer and the SBA).
- (iv)To permit resolution of an appeal by the contracting agency to SBA Headquarters under 19.602-3. However, there is no contracting officer's appeal when the Area Office proposes to issue a COC valued at $100,000 or less.
- (e)At the completion of the process, notify the concern and the contracting officer that the COC is denied or is being issued.
- (f)Refer recommendations for issuing a COC on contracts greater than $25,000,000 to SBA Headquarters.