48 CFR §211.274-3
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)It is DoD policy that contractors shall be required to identify the Government's unit acquisition cost for all deliverable end items to which item unique identification applies.
- (b)The Government's unit acquisition cost is—
- (1)For fixed-price type line, subline, or exhibit line items, the unit price identified in the contract at the time of delivery;
- (2)For cost-type or undefinitized line, subline, or exhibit line items, the contractor's estimated fully burdened unit cost to the Government at the time of delivery; and
- (3)For items delivered under a time-and-materials contract, the contractor's estimated fully burdened unit cost to the Government at the time of delivery.
- (c)The Government's unit acquisition cost of subassemblies, components, and parts embedded in delivered items shall not be separately identified.