48 CFR §219.7103-2
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
Contracting officers shall—
- (a)Negotiate an advance agreement on the treatment of developmental assistance costs for either credit or reimbursement if the mentor firm proposes such an agreement, or delegate authority to negotiate to the administrative contracting officer (see FAR 31.109).
- (b)Modify (without consideration) applicable contract(s) to incorporate the clause at 252.232-7005, Reimbursement of Subcontractor Advance Payments—DoD Mentor-Protégé Program, when a mentor firm provides advance payments to a protégé firm under the Program and the mentor firm requests reimbursement of advance payments.
- (c)Modify (without consideration) applicable contract(s) to incorporate other than customary progress payments for protégé firms in accordance with FAR 32.504(c) if a mentor firm provides such payments to a protégé firm and the mentor firm requests reimbursement.
- (d)Modify applicable contract(s) to establish a contract line item for reimbursement of developmental assistance costs if—
- (e)Negotiate and award a separate contract for reimbursement of developmental assistance costs only if—
- (f)Not authorize reimbursement for costs of assistance furnished to a protégé firm in excess of $1 million in a fiscal year unless a written determination from the Director, OSBP, of the military department or defense agency is obtained.
- (g)Advise contractors of reporting requirements in appendix I.
- (h)Provide a copy of the approved mentor-protégé agreement to the Defense Contract Management Agency (DCMA) small business professional responsible for conducting the annual performance review (see appendix I, section I-113).