- (a)Items shall be removed from contractors' facilities affected by work stoppages in accordance with agency procedures. Agency procedures should allow for the following:
- (1)Determine whether removal of items is in the Government's interest. Normally the determining factor is the critical needs of an agency program.
- (2)Attempt to arrange with the contractor and the union representative involved their approval of the shipment of urgently required items.
- (3)Obtain appropriate approvals from within the agency.
- (4)Determine who will remove the items from the plant(s) involved.
- (b)Avoid the use or appearance of force and prevent incidents that might detrimentally affect labor-management relations.
- (c)When two or more agencies' requirements are or may become involved in the removal of items, the contract administration office shall ensure that the necessary coordination is accomplished.