48 CFR §22.503
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)Executive Order (E.O.) 14063, Use of Project Labor Agreements for Federal Construction Projects, requires agencies to use project labor agreements in large-scale construction projects to promote economy and efficiency in the administration and completion of Federal construction projects.
- (b)When awarding a contract in connection with a large-scale construction project (see 22.502), agencies shall require use of project labor agreements for contractors and subcontractors engaged in construction on the project, unless an exception at 22.504(d) applies.
- (c)An agency may require the use of a project labor agreement on projects where the total cost to the Federal Government is less than that for a large-scale construction project, if appropriate.
- (1)An agency may, if appropriate, require that every contractor and subcontractor engaged in construction on the project agree, for that project, to negotiate or become a party to a project labor agreement with one or more labor organizations if the agency decides that the use of project labor agreements will—
- (i)Advance the Federal Government's interest in achieving economy and efficiency in Federal procurement, producing labor-management stability, and ensuring compliance with laws and regulations governing safety and health, equal employment opportunity, labor and employment standards, and other matters; and
- (ii)Be consistent with law.
- (2)Agencies may consider the following factors in deciding whether the use of a project labor agreement is appropriate for a construction project where the total cost to the Federal Government is less than that for a large-scale construction project:
- (i)The project will require multiple construction contractors and/or subcontractors employing workers in multiple crafts or trades.
- (ii)There is a shortage of skilled labor in the region in which the construction project will be sited.
- (iii)Completion of the project will require an extended period of time.
- (iv)Project labor agreements have been used on comparable projects undertaken by Federal, State, municipal, or private entities in the geographic area of the project.
- (v)A project labor agreement will promote the agency's long term program interests, such as facilitating the training of a skilled workforce to meet the agency's future construction needs.
- (vi)Any other factors that the agency decides are appropriate.
- (1)An agency may, if appropriate, require that every contractor and subcontractor engaged in construction on the project agree, for that project, to negotiate or become a party to a project labor agreement with one or more labor organizations if the agency decides that the use of project labor agreements will—
- (d)For indefinite-delivery indefinite-quantity (IDIQ) contracts the use of a project labor agreement may be required on an order-by-order basis rather than for the entire contract. For an order at or above $35 million an agency shall require the use of a project labor agreement unless an exception applies. See 22.504(d)(3) and 22.505(b)(3).