- (a)Withholding from contract payments. The contracting officer shall contact the labor advisor for assistance when payments due a contractor are not available to satisfy that contractor's liability for Construction Wage Rate Requirements or CWHSS statute wage underpayments or liquidated damages.
- (c)Disposition of contract payments withheld or suspended—(3) Limitation on forwarding or returning funds. When disposition of withheld funds remains the final action necessary to close out a contract, the Department of Labor will retain withheld funds pending completion of an investigation or other administrative proceedings.
- (4)Liquidated damages.
- (A)The agency head may adjust liquidated damages of $500 or less when the amount assessed is incorrect or waive the assessment when the violations—
- (B)The agency head may recommend to the Administrator, Wage and Hour Division, that the liquidated damages over $500 be adjusted because the amount assessed is incorrect. The agency head may also recommend the assessment be waived when the violations—
- (4)Liquidated damages.