48 CFR §4.804-4
- (a)Except as provided in paragraph (b) of this section, a contract is considered to be physically completed when—
- (1)
- (i)The contractor has completed the required deliveries and the Government has inspected and accepted the supplies;
- (ii)The contractor has performed all services and the Government has accepted these services; and
- (iii)All option provisions, if any, have expired; or
- (2)The Government has given the contractor a notice of complete contract termination.
- (b)Rental, use, and storage agreements are considered to be physically completed when—
- (1)The Government has given the contractor a notice of complete contract termination; or
- (2)The contract period has expired.