48 CFR §42.1107

Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov
  1. (a)The contracting officer shall insert the clause at 52.242-2, Production Progress Reports, in solicitations and contracts when production progress reporting is required; unless a construction contract, or a Federal Supply Schedule contract is contemplated.
  2. (b)When the clause at 52.242-2 is used, the contracting officer shall specify appropriate reporting instructions in the Schedule (see 42.1106(a)).