StacksVerified U.S. regulatory reference

48 CFR §49.405

Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov
If the surety does not arrange for completion of the contract, the contracting officer normally will arrange for completion of the work by awarding a new contract based on the same plans and specifications. The new contract may be the result of sealed bidding or any other appropriate contracting method or procedure. The contracting officer shall exercise reasonable diligence to obtain the lowest price available for completion.