StacksVerified U.S. regulatory reference

48 CFR §53.209-1

Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov
The following forms are prescribed for use in conducting preaward surveys of prospective contractors, as specified in 9.106-1, 9.106-2, and 9.106-4. These forms are authorized for local reproduction and can be found at the GSA Forms Library at https://www.gsa.gov/forms.
  1. (a)SF 1403 (Rev. 01/2014), Preaward Survey of Prospective Contractor (General).
  2. (b)SF 1404 (Rev. 01/2014), Preaward Survey of Prospective Contractor—Technical.
  3. (c)SF 1405 (Rev. 01/2014), Preaward Survey of Prospective Contractor—Production.
  4. (d)SF 1406 (Rev. 01/2014), Preaward Survey of Prospective Contractor—Quality Assurance.
  5. (e)SF 1407 (Rev. 01/2014), Preaward Survey of Prospective Contractor—Financial Capability.
  6. (f)SF 1408 (Rev. 01/2014), Preaward Survey of Prospective Contractor—Accounting System.