48 CFR §532.904
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
Payment due dates for construction contracts are addressed at FAR 32.904(d). The following procedures apply to construction and building service contracts:
- (a)The amount of final payment must include, as appropriate, deductions to cover any of the following:
- (1)Liquidated damages for late completion.
- (2)Liquidated damages for labor violations.
- (3)Amounts withheld for improper payment of labor wages.
- (4)The amount of unilateral change orders covering defects and omissions.
- (5)The agreed-upon dollar amount in a Deficiency Report, which is included in all applicable Operation and Maintenance (O&M) service contracts.
- (b)An official one level above the contracting officer shall approve justifications exercising the authority prescribed by FAR 32.904(d)(1)(i)(B). The time needed should be determined on a case-by-case basis, but the specified constructive acceptance period shall not exceed 30 days.