48 CFR §536.515
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
Insert the clause at 552.236-15, Schedules for Construction Contracts, in solicitations and contracts if construction, dismantling, demolition, or removal of improvements is contemplated. Use the clause:
- (a)With its Alternate I when the contract amount is expected to exceed the simplified acquisition threshold and a design-bid-build project delivery method will be followed.
- (b)With its Alternate II when the contract amount is expected to exceed the simplified acquisition threshold and a design-build project delivery method will be followed.
- (c)With its Alternate III when the contract amount is expected to exceed the simplified acquisition threshold and a construction-manager-as-constructor project delivery method will be followed.