48 CFR §570.402-5
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
If the contracting officer identifies potential acceptable locations through the advertisement or market survey, conduct a cost-benefit analysis following the procedures in 570.402-6. Based on the results of the cost-benefit analysis, take appropriate action as follows:
- (a)If the cost-benefit analysis indicates that the Government will recover relocation costs and duplication of costs through competition, develop an SFO and negotiate with all interested parties following 570.3.
- (b)If the cost-benefit analysis indicates that the Government cannot expect to recover relocation costs and duplication of costs through competition, prepare a justification for approval in accordance with FAR 6.3 and 506.3. Explain both: