Contracting officers shall, in appropriate circumstances, follow the requirements in FAR subpart 22.1, as supplemented in this section, in the award and administration of:
- (a)Management and operating (M&O) contracts;
- (b)Contracts the Senior Procurement Executive designates; and
- (c)Non-M&O contracts where the current contract's work was previously performed under an M&O contract and the current Contractor was required to, and did, employ the former Contractor's legacy workforce. These non-M&O contracts may include, but are not limited to, contracts whose work is for:
- (1)Environmental remediation;
- (2)Decontamination and decommissioning;
- (3)Environmental restoration;
- (4)Infrastructure services for the site;
- (5)Site closure at a current or former M&O contract site or facility; or
- (6)Protective forces that provide physical security of sites at a current of former M&O contract site or facility.