48 CFR §970.4207-501
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (b)
- (4)A contracting officer shall not resolve any questioned costs until the contracting officer has obtained—
- (5)The contracting officer shall ensure that the documentation supporting the final settlement addresses the amount of the questioned costs and the subsequent disposition of such questioned costs.
- (6)The contracting officer shall ensure, to the maximum extent practicable, that the Department of Energy's auditor is afforded an opportunity to attend any negotiation or meeting with the contractor regarding a determination of allowability.