As specified in §63.8095, the parts of the General Provisions that apply to you are shown in the following table:
Open Table
Citation | Subject | Explanation |
---|---|---|
§63.1 | Applicability | Yes. |
§63.2 | Definitions | Yes. |
§63.3 | Units and Abbreviations | Yes. |
§63.4 | Prohibited Activities | Yes. |
§63.5 | Construction/Reconstruction | Yes. |
§63.6(a) | Applicability | Yes. |
§63.6(b)(1)-(4) | Compliance Dates for New and Reconstructed sources | Yes. |
§63.6(b)(5) | Notification | Yes. |
§63.6(b)(6) | [Reserved] | |
§63.6(b)(7) | Compliance Dates for New and Reconstructed Area Sources That Become Major | Yes. |
§63.6(c)(1)-(2) | Compliance Dates for Existing Sources | Yes. |
§63.6(c)(3)-(4) | [Reserved] | |
§63.6(c)(5) | Compliance Dates for Existing Area Sources That Become Major | Yes. |
§63.6(d) | [Reserved] | |
§63.6(e)(1)-(2) | Operation & Maintenance | Yes. |
§63.6(e)(3)(i), (ii), and (v) through (viii) | SSMP | Yes, except information regarding Group 2 emission points and equipment leaks is not required in the SSMP, as specified in §63.8080(f). |
§63.6(e)(3)(iii) and (iv) | Recordkeeping and Reporting During Startup, Shutdown, and Malfunction (SSM) | No, §§63.998(d)(3) and 63.998(c)(1)(ii)(D) through (G) specify the recordkeeping requirement for SSM events, and §63.8075(e)(5) specifies reporting requirements. |
§63.6(e)(3)(ix) | Title V permit | Yes. |
§63.6(f)(1) | Compliance Except During SSM | Yes. |
§63.6(f)(2)-(3) | Methods for Determining Compliance | Yes. |
§63.6(g)(1)-(3) | Alternative Standard | Yes. |
§63.6(h) | Opacity/Visible Emission (VE) Standards | Only for flares for which Method 22 observations are required as part of a flare compliance assessment. |
§63.6(i)(1)-(14) | Compliance Extension | Yes. |
§63.6(j) | Presidential Compliance Exemption | Yes. |
§63.7(a)(1)-(2) | Performance Test Dates | Yes, except substitute 150 days for 180 days. |
§63.7(a)(3) | CAA Section 114 Authority | Yes, and this paragraph also applies to flare compliance assessments as specified under §63.997(b)(2). |
§63.7(b)(1) | Notification of Performance Test | Yes. |
§63.7(b)(2) | Notification of Rescheduling | Yes. |
§63.7(c) | Quality Assurance/Test Plan | Yes, except the test plan must be submitted with the notification of the performance test if the control device controls process vessels. |
§63.7(d) | Testing Facilities | Yes. |
§63.7(e)(1) | Conditions for Conducting Performance Tests | Yes, except that performance tests for process vessels must be conducted under worst-case conditions as specified in §63.8005. |
§63.7(e)(2) | Conditions for Conducting Performance Tests | Yes. |
§63.7(e)(3) | Test Run Duration | Yes. |
§63.7(f) | Alternative Test Method | Yes. |
§63.7(g) | Performance Test Data Analysis | Yes. |
§63.7(h) | Waiver of Tests | Yes. |
§63.8(a)(1) | Applicability of Monitoring Requirements | Yes. |
§63.8(a)(2) | Performance Specifications | Yes. |
§63.8(a)(3) | [Reserved] | |
§63.8(a)(4) | Monitoring with Flares | Yes. |
§63.8(b)(1) | Monitoring | Yes. |
§63.8(b)(2)-(3) | Multiple Effluents and Multiple Monitoring Systems | Yes. |
§63.8(c)(1) | Monitoring System Operation and Maintenance | Yes. |
§63.8(c)(1)(i) | Maintain and operate CMS | Yes. |
§63.8(c)(1)(ii) | Routine repairs | Yes. |
§63.8(c)(1)(iii) | SSMP for CMS | Yes. |
§63.8(c)(2)-(3) | Monitoring System Installation | Yes. |
§63.8(c)(4) | Requirements | Only for CEMS; requirements for CPMS are specified in referenced subpart SS of 40 CFR part 63. This subpart does not contain requirements for continuous opacity monitoring systems (COMS). |
§63.8(c)(4)(i) | CMS Requirements | No. This subpart does not require COMS. |
§63.8(c)(4)(ii) | CMS requirements | Yes. |
§63.8(c)(5) | COMS Minimum Procedures | No. This subpart does not contain opacity or VE limits. |
§63.8(c)(6) | CMS Requirements | Only for CEMS; requirements for CPMS are specified in referenced subpart SS of 40 CFR part 63. |
§63.8(c)(7)-(8) | CMS Requirements | Only for CEMS. Requirements for CPMS are specified in referenced subpart SS of 40 CFR part 63. |
§63.8(d) | CMS Quality Control | Only for CEMS; requirements for CPMS are specified in referenced subpart SS of 40 CFR part 63. |
§63.8(e) | CMS Performance Evaluation | Section 63.8(e)(6)(ii) does not apply because this subpart does not require COMS. Other sections apply only for CEMS; requirements for CPMS are specified in referenced subpart SS of 40 CFR part 63. |
§63.8(f)(1)-(5) | Alternative Monitoring Method | Yes, except you may also request approval using the precompliance report. |
§63.8(f)(6) | Alternative to Relative Accuracy Test | Only for CEMS. |
§63.8(g)(1)-(4) | Data Reduction | Only when using CEMS, except §63.8(g)(2) does not apply because data reduction requirements for CEMS are specified in §63.8000(d)(4)(iv). |
The requirements for COMS do not apply because this subpart has no opacity or VE limits. | ||
§63.8(g)(5) | Data Reduction | No. Requirements for CEMS are specified in §63.8000(d)(4). |
Requirements for CPMS are specified in referenced subpart SS of 40 CFR part 63. | ||
§63.9(a) | Notification Requirements | Yes. |
§63.9(b)(1)-(5) | Initial Notifications | Yes. |
§63.9(c) | Request for Compliance Extension | Yes. |
§63.9(d) | Notification of Special Compliance Requirements for New Source | Yes. |
§63.9(e) | Notification of Performance Test | Yes. |
§63.9(f) | Notification of VE/Opacity Test | No. This subpart does not contain opacity or VE limits. |
§63.9(g) | Additional Notifications When Using CMS | Only for CEMS; requirements for CPMS are specified in referenced subpart SS of 40 CFR part 63. |
§63.9(h)(1)-(6) | Notification of Compliance Status | Yes, except this subpart has no opacity or VE limits, and §63.9(h)(2) does not apply because §63.8075(d) specifies the required contents and due date of the notification of compliance status report. |
§63.9(i) | Adjustment of Submittal Deadlines | Yes. |
§63.9(j) | Change in Previous Information | No, §63.8075(e)(8) specifies reporting requirements for process changes. |
§63.10(a) | Recordkeeping/Reporting | Yes. |
§63.10(b)(1) | Recordkeeping/Reporting | Yes. |
§63.10(b)(2)(i)-(iv) | Records related to SSM | No, §§63.998(d)(3) and 63.998(c)(1)(ii)(D) through (G) specify recordkeeping requirements for periods of SSM. |
§63.10(b)(2)(iii) | Records related to maintenance of air pollution control equipment | Yes. |
§63.10(b)(2)(vi), (x), and (xi) | CMS Records | Only for CEMS; requirements for CPMS are specified in referenced subpart SS of 40 CFR part 63. |
§63.10(b)(2)(vii)-(ix) | Records | Yes. |
§63.10(b)(2)(xii) | Records | Yes. |
§63.10(b)(2)(xiii) | Records | Yes. |
§63.10(b)(2)(xiv) | Records | Yes. |
§63.10(b)(3) | Records | Yes. |
§63.10(c)(1)-(6),(9)-(15) | Records | Only for CEMS; requirements for CPMS are specified in referenced subpart SS of 40 CFR part 63. |
§63.10(c)(7)-(8) | Records | No. Recordkeeping requirements are specified in §63.8080. |
§63.10(d)(1) | General Reporting Requirements | Yes. |
§63.10(d)(2) | Report of Performance Test Results | Yes. |
§63.10(d)(3) | Reporting Opacity or VE Observations | No. This subpart does not contain opacity or VE limits. |
§63.10(d)(4) | Progress Reports | Yes. |
§63.10(d)(5)(i) | SSM Reports | No, §63.8075(e)(5) and (6) specify the SSM reporting requirements. |
§63.10(d)(5)(ii) | Immediate SSM reports | No. |
§63.10(e)(1)-(2) | Additional CMS Reports | Only for CEMS, but §63.10(e)(2)(ii) does not apply because this subpart does not require COMS. |
§63.10(e)(3) | Reports | No. Reporting requirements are specified in §63.8075. |
§63.10(e)(3)(i)-(iii) | Reports | No. Reporting requirements are specified in §63.8075. |
§63.10(e)(3)(iv)-(v) | Excess Emissions Reports | No. Reporting requirements are specified in §63.8075. |
§63.10(e)(3)(vi-viii) | Excess Emissions Report and Summary Report | No. Reporting requirements are specified in §63.8075. |
§63.10(e)(4) | Reporting COMS data | No. This subpart does not contain opacity or VE limits. |
§63.10(f) | Waiver for Recordkeeping/Reporting | Yes. |
§63.11 | Control and work practice requirements | Yes |
§63.12 | Delegation | Yes. |
§63.13 | Addresses | Yes. |
§63.14 | Incorporation by Reference | Yes. |
§63.15 | Availability of Information | Yes. |
[68 FR 69185, Dec. 11, 2003, as amended at 71 FR 20468, Apr. 20, 2006; 73 FR 78216, Dec. 22, 2008]