As required in §63.8075(a) and (b), you must submit each report that applies to you on the schedule shown in the following table:

Open Table
You must submit a .  .  . The report must contain .  .  . You must submit the report .  .  .
1. Precompliance report The information specified in §63.8075(c) At least 6 months prior to the compliance date; or for new sources, with the application for approval of construction or reconstruction.
2. Notification of compliance status report The information specified in §63.8075(d) No later than 150 days after the compliance date specified in §63.7995.
3. Compliance report The information specified in §63.8075(e) Semiannually according to the requirements in §63.8075(b).