40 CFR Table 11
Applicability of General Provisions to Subpart SSSSS
June 9, 2020
As stated in §63.9820, you must comply with the applicable General Provisions requirements according to the following table:
Open Table
Citation | Subject | Brief description | Applies to subpart SSSSS |
---|---|---|---|
§63.1 | Applicability | Yes. | |
§63.2 | Definitions | Yes. | |
§63.3 | Units and Abbreviations | Yes. | |
§63.4 | Prohibited Activities | Compliance date; circumvention, severability | Yes. |
§63.5 | Construction/Reconstruction | Applicability; applications; approvals | Yes. |
§63.6(a) | Applicability | General Provisions (GP) apply unless compliance extension; GP apply to area sources that become major | Yes. |
§63.6(b)(1)-(4) | Compliance Dates for New and Reconstructed Sources | Standards apply at effective date; 3 years after effective date; upon startup; 10 years after construction or reconstruction commences for section 112(f) | Yes. |
§63.6(b)(5) | Notification | Yes. | |
§63.6(b)(6) | [Reserved] | ||
§63.6(b)(7) | Compliance Dates for New and Reconstructed Area Sources That Become Major | Area sources that become major must comply with major source standards immediately upon becoming major, regardless of whether required to comply when they were area sources | Yes. |
§63.6(c)(1)-(2) | Compliance Dates for Existing Sources | Comply according to date in subpart, which must be no later than 3 years after effective date; for section 112(f) standards, comply within 90 days of effective date unless compliance extension | Yes. |
§63.6(c)(3)-(4) | [Reserved] | ||
§63.6(c)(5) | Compliance Dates for Existing Area Sources That Become Major | Area sources that become major must comply with major source standards by date indicated in subpart or by equivalent time period (for example, 3 years) | Yes. |
§63.6(d) | [Reserved] | ||
§63.6(e)(1)-(2) | Operation & Maintenance | Operate to minimize emissions at all times; correct malfunctions as soon as practicable; requirements independently enforceable; information Administrator will use to determine if operation and maintenance requirements were met | Yes. |
§63.6(e)(3) | Startup, Shutdown, and Malfunction Plan (SSMP) | Yes. | |
§63.6(f)(1) | Compliance Except During SSM | You must comply with emission standards at all times except during SSM | Yes. |
§63.6(f)(2)-(3) | Methods for Determining Compliance | Compliance based on performance test, operation and maintenance plans, records, inspection | Yes. |
§63.6(g)(1)-(3) | Alternative Standard | Procedures for getting an alternative standard. | Yes. |
§63.6(h)(1)-(9) | Opacity/Visible Emission (VE) Standards | Not applicable. | |
§63.6(i)(1)-(14) | Compliance Extension | Procedures and criteria for Administrator to grant compliance extension | Yes. |
§63.6(j) | Presidential Compliance Exemption | President may exempt source category | Yes. |
§63.7(a)(1)-(2) | Performance Test Dates | Dates for conducting initial performance testing and other compliance demonstrations; must conduct 180 days after first subject to rule | Yes. |
§63.7(a)(3) | Section 114 Authority | Administrator may require a performance test under CAA section 114 at any time | Yes. |
§63.7(b)(1) | Notification of Performance Test | Must notify Administrator 60 days before the test | Yes. |
§63.7(b)(2) | Notification of Rescheduling | Must notify Administrator 5 days before scheduled date and provide rescheduled date | Yes. |
§63.7(c) | Quality Assurance/Test Plan | Requirements; test plan approval procedures; performance audit requirements; internal and external QA procedures for testing | Yes. |
§63.7(d) | Testing Facilities | Yes. | |
§63.7(e)(1) | Conditions for Conducting Performance Tests | Performance tests must be conducted under representative conditions; cannot conduct performance tests during SSM; not a violation to exceed standard during SSM | No, §63.9800 specifies requirements; Yes; Yes. |
§63.7(e)(2) | Conditions for Conducting Performance Tests | Must conduct according to subpart and EPA test methods unless Administrator approves alternative | Yes. |
§63.7(e)(3) | Test Run Duration | Must have three test runs of at least 1 hour each; compliance is based on arithmetic mean of three runs; conditions when data from an additional test run can be used | Yes; Yes, except where specified in §63.9800 for batch process sources; Yes. |
§63.7(f) | Alternative Test Method | Yes. | |
§63.7(g) | Performance Test Data Analysis | Yes. | |
§63.7(h) | Waiver of Test | Yes. | |
§63.8(a)(1) | Applicability of Monitoring Requirements | Yes. | |
§63.8(a)(2) | Performance Specifications | Performance Specifications in appendix B of 40 CFR part 60 apply | Yes. |
§63.8(a)(3) | [Reserved] | ||
§63.8(a)(4) | Monitoring with Flares | Not applicable. | |
§63.8(b)(1) | Monitoring | Must conduct monitoring according to standard unless Administrator approves alternative | Yes. |
§63.8(b)(2)-(3) | Multiple Effluents and Multiple Monitoring Systems | Specific requirements for installing and reporting on monitoring systems | Yes. |
§63.8(c)(1) | Monitoring System Operation and Maintenance | Maintenance consistent with good air pollution control practices | Yes. |
§63.8(c)(1)(i) | Routine and Predictable SSM | Reporting requirements for SSM when action is described in SSMP | Yes. |
§63.8(c)(1)(ii) | SSM not in SSMP | Reporting requirements for SSM when action is not described in SSMP | Yes. |
§63.8(c)(1)(iii) | Compliance with Operation and Maintenance Requirements | How Administrator determines if source is complying with operation and maintenance requirements | Yes. |
§63.8(c)(2)-(3) | Monitoring System Installation | Must install to get representative emission and parameter measurements | Yes. |
§63.8(c)(4) | CMS Requirements | No, §63.9808 specifies requirements. | |
§63.8(c)(5) | COMS Minimum Procedures | Not applicable. | |
§63.8(c)(6) | CMS Requirements | Applies only to sources required to install and operate a THC CEMS. | |
§63.8(c)(7)(i)(A) | CMS Requirements | Applies only to sources required to install and operate a THC CEMS. | |
§63.8(c)(7)(i)(B) | CMS Requirements | Applies only to sources required to install and operate a THC CEMS. | |
§63.8(c)(7)(i)(C) | CMS Requirements | Not applicable. | |
§63.8(c)(7)(ii) | CMS Requirements | Corrective action required when CMS is out of control | Yes. |
§63.8(c)(8) | CMS Requirements | Yes. | |
§63.8(d) | CMS Quality Control | Applies only to sources required to install and operate a THC CEMS. | |
§63.8(e) | CMS Performance Evaluation | Applies only to sources required to install and operate a THC CEMS. | |
§63.8(f)(1)-(5) | Alternative Monitoring Method | Yes. | |
§63.8(f)(6) | Alternative to Relative Accuracy Test | Yes. | |
§63.8(g) | Data Reduction | Applies only to sources required to install and operate a THC CEMS. | |
§63.9(a) | Notification Requirements | Yes. | |
§63.9(b)(1)-(5) | Initial Notifications | Yes. | |
§63.9(c) | Request for Compliance Extension | Yes. | |
§63.9(d) | Notification of Special Compliance Requirements for New Source | Yes. | |
§63.9(e) | Notification of Performance Test | Notify Administrator 60 days prior | Yes. |
§63.9(f) | Notification of VE/Opacity Test | Not applicable. | |
§63.9(g) | Additional Notifications When Using CMS | Applies only to sources required to install and operate a THC CEMS. | |
§63.9(h) | Notification of Compliance Status | Yes. | |
§63.9(i) | Adjustment of Submittal Deadlines | Yes. | |
§63.9(j) | Change in Previous Information | Yes. | |
§63.10(a) | Recordkeeping/Reporting | Yes. | |
§63.10(b)(1) | Recordkeeping/Reporting | Yes. | |
§63.10(b)(2)(i)-(v) | Records Related to Startup, Shutdown, and Malfunction | Yes. | |
§63.10(b)(2)(vi) and (x-xi) | CMS Records | Yes. | |
§63.10(b)(2)(vii)-(ix) | Records | Measurements to demonstrate compliance with emission limitations; performance test, performance evaluation, and visible emission observation results; measurements to determine conditions of performance tests and performance evaluations | Yes. |
§63.10(b)(2)(xii) | Records | Records when under waiver | Yes. |
§63.10(b)(2)(xiii) | Records | Records when using alternative to relative accuracy test | Not applicable. |
§63.10(b)(2)(xiv) | Records | All documentation supporting Initial Notification and Notification of Compliance Status | Yes. |
§63.10(b)(3) | Records | Applicability Determinations | Yes. |
§63.10(c)(1)-(6), (9)-(15) | Records | Additional Records for CMS | Not applicable. |
§63.10(c)(7)-(8) | Records | Records of excess emissions and parameter monitoring exceedances for CMS | No, §63.9816 specifies requirements. |
§63.10(d)(1) | General Reporting Requirements | Requirements for reporting | Yes. |
§63.10(d)(2) | Report of Performance Test Results | When to submit to Federal or State authority | Yes. |
§63.10(d)(3) | Reporting Opacity or VE Observations | Not applicable. | |
§63.10(d)(4) | Progress Reports | Must submit progress reports on schedule if under compliance extension | Yes. |
§63.10(d)(5) | Startup, Shutdown, and Malfunction Reports | Contents and submission | Yes. |
§63.10(e)(1)-(2) | Additional CMS Reports | Applies only to sources required to install and operate a THC CEMS. | |
§63.10(e)(3) | Reports | No, §63.9814 specifies requirements. | |
§63.10(e)(4) | Reporting COMS data | Not applicable. | |
§63.10(f) | Waiver for Recordkeeping/Reporting | Yes. | |
§63.11 | Flares | Not applicable. | |
§63.12 | Delegation | Yes. | |
§63.13 | Addresses | Yes. | |
§63.14 | Incorporation by Reference | Yes. | |
§63.15 | Availability of Information | Yes. |