40 CFR Table 10
Requirements for Reports
June 9, 2020
As stated in §63.9814, you must comply with the requirements for reports in the following table:
Open Table
You must submit a(n) . . . | The report must contain . . . | You must submit the report . . . |
---|---|---|
1. Compliance report | The information in §63.9814(c) through (f) | Semiannually according to the requirements in §63.9814(a) through (f). |
2. Immediate startup, shutdown, and malfunction report if you had a startup, shutdown, or malfunction during the reporting period that is not consistent with your SSMP | a. Actions taken for the event | By fax or telephone within 2 working days after starting actions inconsistent with the plan. |
b. The information in §63.10(d)(5)(ii) | By letter within 7 working days after the end of the event unless you have made alternative arrangements with the permitting authority. | |
3. Report of alternative fuel use | The information in §63.9814(g) and items 4 and 5 of Table 9 to this subpart | If you are subject to the work practice standard specified in item 3 or 4 of Table 3 to this subpart, and you use an alternative fuel in the affected kiln, by letter within 10 working days after terminating the use of the alternative fuel. |