As stated in §63.6010, you must submit each report that applies to you according to the following table:
Open Table
You must submit a(n) | The report must contain . . . | You must submit the report . . . |
---|---|---|
1. Compliance report | a. If there are no deviations from any emission limitations that apply to you, a statement that there were no deviations from the emission limitations during the reporting period. If there were no periods during which the CPMS was out-of-control as specified in §63.8(c)(7), a statement that there were no periods during which the CPMS was out-of-control during the reporting period | Semiannually according to the requirements in §63.6010(b), unless you meet the requirements for annual reporting in §63.6010(f). |
b. If you have a deviation from any emission limitation during the reporting period at an affected source where you are not using a CPMS, the report must contain the information in §63.6010(d). If the deviation occurred at a source where you are using a CMPS or if there were periods during which the CPMS were out-of-control as specified in §63.8(c)(7), the report must contain the information required by §63.5990(f)(3) | Semiannually according to the requirements in §63.6010(b), unless you meet the requirements for annual reporting in §63.6010(f). | |
c. If you had a startup, shutdown or malfunction during the reporting period and you took actions consistent with your startup, shutdown, and malfunction plan, the compliance report must include the information in §63.10(d)(5)(i) | Semiannually according to the requirements in §63.6010(b), unless you meet the requirements for annual reporting in §63.6010(f). | |
2. Immediate startup, shutdown, and malfunction report if you had a startup, shutdown, or malfunction during the reporting period that is not consistent with your startup, shutdown, and malfunction plan. | a. Actions taken for the event | By fax or telephone within 2 working days after starting actions inconsistent with the plan. |
b. The information in §63.10(d)(5)(ii) | By letter within 7 working days after the end of the event unless you have made alternative arrangements with the permitting authority (§63.10(d)(5)(ii)). |