For the following new sources .  .  . You must meet the emission limits for the specified pollutant .  .  .
Total fluorides
Phosphate Fertilizer Process Line (e.g., Diammonium and/or Monoammonium Phosphate Process Line) 0.0580 lb/ton of equivalent P2O5 feed.
Granular Triple Superphosphate Process Line 0.1230 lb/ton of equivalent P2O5 feed.
GTSP storage building 5.0 × 10−4 lb/hr/ton of equivalent P2O5 stored.

aThe new source compliance dates are based on date of construction or reconstruction as specified in §63.622(a).

bDuring periods of startup and shutdown, for emission limits stated in terms of pounds of pollutant per ton of feed, you are subject to the work practice standards specified in §63.622(d).