40 CFR Table 2
Applicability of General Provisions to Subpart TTTT
June 9, 2020
As required in §63.5450, you must meet the appropriate NESHAP General Provision requirements in the following table:
Open Table
General provisions citation | Subject of citation | Brief description of requirement | Applies to subpart |
Explanation |
---|---|---|---|---|
§63.1 | Applicability | Initial applicability determination; applicability after standard established; permit requirements; extensions, notifications. | Yes | |
§63.2 | Definitions | Definitions for Part 63 standards | Yes | Except as specifically provided in this subpart. |
§63.3 | Units and abbreviations | Units and abbreviations for Part 63 standards | Yes | |
§63.4 | Prohibited activities and circumvention | Prohibited activities; compliance date; circumvention, severability | Yes | |
§63.5 | Construction/reconstruction | Applicability; applications; approvals | Yes | Except for paragraphs of §63.5 as listed below. |
§63.5(c) | [Reserved] | |||
§63.5(d)(1)(ii)(H) | Application for approval | Type and quantity of HAP, operating parameters. | No | All sources emit HAP. Subpart TTTT does not require control from specific emission points. |
§63.5(d)(1)(i) | [Reserved]. | |||
§63.5(d)(1)(iii), (d)(2), (d)(3)(ii) | Application for approval | No | The requirements of the application for approval for new and reconstructed sources are described in §63.5320(b). General provision requirements for identification of HAP emission points or estimates of actual emissions are not required. Descriptions of control and methods, and the estimated and actual control efficiency of such do not apply. Requirements for describing control equipment and the estimated and actual control efficiency of such equipment apply only to control equipment to which the subpart TTTT requirements for quantifying solvent destroyed by an add-on control device would be applicable. | |
§63.6 | Applicability of general provisions | Applicability of general provisions | Yes | Except for paragraphs of §63.6 as listed below. |
§63.6(b)(1)-(3) | Compliance dates, new and reconstructed sources | No | Section §63.5283 specifies the compliance dates for new and reconstructed sources. | |
§63.6(b)(6) | [Reserved]. | |||
§63.6(c)(3)-(4) | [Reserved]. | |||
§63.6(d) | [Reserved]. | |||
§63.6(e)(1) | Operation and maintenance requirements | No | See §63.5320(b) for general duty requirement. | |
§63.6(e)(2) | [Reserved] | |||
§63.6(e)(3) | Operation and maintenance requirements | Startup, shutdown, and malfunction plan requirements | No | Subpart TTTT does not have any startup, shutdown, and malfunction plan requirements. |
§63.6(f)-(g) | Compliance with nonopacity emission standards except during SSM | Comply with emission standards at all times except during SSM | No | Subpart TTTT does not have nonopacity requirements. |
§63.6(h) | Opacity/visible emission (VE) standards | No | Subpart TTTT has no opacity or visual emission standards. | |
§63.6(i) | Compliance extension | Procedures and criteria for responsible agency to grant compliance extension | Yes | |
§63.6(j) | Presidential compliance exemption | President may exempt source category from requirement to comply with subpart | Yes | |
§63.7 | Performance testing requirements | Schedule, conditions, notifications and procedures | Yes | Except for paragraphs of §63.7 as listed below. Subpart TTTT requires performance testing only if the source applies additional control that destroys solvent. §63.5311 requires sources to follow the performance testing guidelines of the General Provisions if a control is added. |
§63.7(a)(2) (i) and (iii) | Performance testing requirements | Applicability and performance dates | No | §63.5310(a) of subpart TTTT specifies the requirements of performance testing dates for new and existing sources. |
§63.7(e)(1) | Conduct of performance tests | Defines representative conditions; provides an exemption from the standards for periods of startup, shutdown, and malfunction; requires that, upon request, the owner or operator shall make available to the Administrator such records as may be necessary to determine the conditions of performance tests | No | See §63.5380. |
§63.8 | Monitoring requirements | Applicability, conduct of monitoring, operation and maintenance, quality control, performance evaluations, use of alternative monitoring method, reduction of monitoring data | No | See §63.5360(a)(2) for monitoring requirements. |
§63.9 | Notification requirements | Applicability and State delegation | Yes | Except for paragraphs of §63.9 as listed below. |
§63.9(e) | Notification of performance test | Notify responsible agency 60 days ahead | Yes | Applies only if performance testing is performed. |
§63.9(f) | Notification of VE/opacity observations | Notify responsible agency 30 days ahead | No | Subpart TTTT has no opacity or visual emission standards. |
§63.9(g) | Additional notifications when using a continuous monitoring system (CMS) | Notification of performance evaluation; notification using COMS data; notification that exceeded criterion for relative accuracy | No | See §63.5360(a)(2) for CMS requirements. |
§63.9(h) | Notification of compliance status | Contents | No | §63.5320(d) specifies requirements for the notification of compliance status. |
§63.10 | Recordkeeping/reporting | Schedule for reporting, record storage | Yes | Except for paragraphs of §63.10 as listed below. |
§63.10(b)(2) | Recordkeeping | CMS recordkeeping; CMS records of startup, shutdown, and malfunction events | No | See §63.5360 for CMS recordkeeping requirements, except see §63.5430(h) for CMS recordkeeping requirements if there is a deviation from the standard. |
§63.10(c) | Recordkeeping | Additional CMS recordkeeping | No | See §63.5360(a)(2) for CMS recordkeeping requirements. |
§63.10(d)(2) | Reporting | Reporting performance test results | Yes | Applies only if performance testing is performed. |
§63.10(d)(3) | Reporting | Reporting opacity or VE observations | No | Subpart TTTT has no opacity or visible emission standards. |
§63.10(d)(4) | Reporting | Progress reports | Yes | Applies if a condition of compliance extension. |
§63.10(d)(5) | Reporting | Startup, shutdown, and malfunction reporting | No | See §63.5420(b) for reporting requirements if there is a deviation from the standard. |
§63.10(e) | Reporting | Additional CMS reports | No | See §63.5360(a)(2) for monitoring requirements. |
§63.11 | Control device requirements | Requirements for flares | Yes | Applies only if your source uses a flare to control solvent emissions. Subpart TTTT does not require flares. |
§63.12 | State authority and delegations | State authority to enforce standards | Yes | |
§63.13 | State/regional addresses | Addresses where reports, notifications, and requests are sent | Yes | |
§63.14 | Incorporation by reference | Test methods incorporated by reference | Yes | |
§63.15 | Availability of information and confidentiality | Public and confidential information | Yes |
[84 FR 3322, Feb. 12, 2019]