40 CFR Table 4 to Subpart FFF of Part 62
Generic Compliance Schedule and Increments of Progress (Pre-1987 MWCs)
June 9, 2020
Open Table
Affected facilities | Increment 1 Submit final control plan |
Increment 2 Award contracts |
Increment 3 Begin on-site construction |
Increment 4 Complete on-site construction |
Increment 5 Final compliance |
---|---|---|---|---|---|
Affected facilities that commenced construction, modification, or reconstruction on or before June 26, 1987 (All pollutants) | January 11, 1999 | 05/18/99 | 11/16/99 | 11/19/00 | 12/19/00 |
aTable 4 or 5 of this subpart applies to MWC units subject to the Federal plan except those with site-specific compliance schedules shown in Table 6 of this subpart.
bAs an alternative to this schedule, the owner or operator may close the affected facility by December 19, 2000, complete the retrofit while the affected facility is closed, and achieve final compliance upon restarting. See §§62.14108(c), 62.14108(d), and 62.14109(i) of this subpart.