[Post-1987 MWCs]a b

Open Table
Affected facilities Increment 1
Submit final control plan
Increment 2
Award
contracts
Increment 3
Begin on-site construction
Increment 4
Complete on-site construction
Increment 5
Final compliance
Affected facilities that commenced construction modification, or reconstruction after June 26, 1987:
1. Emission limits for Hg, dioxin/furan NAc NAc NAc NAc 11/12/99 or 1 year after permit issuanced e
2. Emission limits for SO2, HCl, PM, Pb, Cd, opacity CO, NOX January 11, 1999 05/18/99 11/16/99 11/19/00 12/19/00.

aTable 4 or 5 of this subpart applies to MWC units subject to the Federal plan except those with site-specific compliance schedules shown in table 6 of this subpart.

bAs an alternative to this schedule, the unit may close by December 19, 2000, complete retrofit while closed, and achieve final compliance upon restarting. See §§62.14108(c), 62.14108(d), and 62.14109(i) of this subpart.

cBecause final compliance is achieved in 1 year, no increments of progress are required.

dPermit issuance is issuance of a revised construction permit or revised operating permit, if a permit modification is required to retrofit controls.

eFinal compliance must be achieved no later than December 19, 2000, even if the date “1 year after permit issuance” exceeds December 19, 2000.

[63 FR 63202, Nov. 12, 1998, as amended at 65 FR 33468, May 24, 2000]