As specified in §63.5761(a), you must submit notifications according to the following table:

Open Table
If your facility— You must submit— By this date—
1. Is an existing source subject to this subpart An initial notification containing the information specified in §63.9(b)(2) No later than the dates specified in §63.9(b)(2).
2. Is a new source subject to this subpart The notifications specified in §63.9(b) (3) to (5) No later than the dates specified §63.9(b)(4) and (5).
3. Qualifies for a compliance extension as specified in §63.9(c) A request for a compliance extension as specified in §63.9(c) No later than the dates specified in §63.6(i).
4. Is complying with organic HAP content limits, application equipment requirements; or MACT model point value averaging provisions A notification of compliance status as specified in §63.9(h) No later than 30 calendar days after the end of the first 12-month averaging period after your facility's compliance date.
5. Is complying by using an add-on control device a. notification of intent to conduct a performance test as specified in §63.9(e) No later than the date specified in §63.9(e).
    b. A notification of the date for the continuous monitoring system performance evaluation as specified in §63.9(g) With the notification of intent to conduct a performance test.
    c. A notification of compliance status as specified in §63.9(h) No later than 60 calendar days after the completion of the add-on control device performance test and continuous monitoring system performance evaluation.