40 CFR Table 7
Notifications
June 9, 2020
As required in §§63.5490(c)(4), 63.5530(c), 63.5575, and 63.5595(b), you must submit the appropriate notifications specified in the following table:
Open Table
If you . . . | then you must . . . |
---|---|
1. are required to conduct a performance test | submit a notification of intent to conduct a performance test at least 60 calendar days before the performance test is scheduled to begin, as specified in §§63.7(b)(1) and 63.9(e). |
2. wish to use an alternative monitoring method | submit a request to use alternative monitoring method no later than the notification of the initial performance test or CEMS performance evaluation or 60 days prior to any other initial compliance demonstration, as specified in §63.8(f)(4). |
3. start up your affected source before June 11, 2002 | submit an initial notification no later than 120 days after June 11, 2002, as specified in §63.9(b)(2). |
4. start up your new or reconstructed source on or after June 11, 2002 | submit an initial notification no later than 120 days after you become subject to this subpart, as specified in §63.9(b)(3). |
5. cannot comply with the relevant standard by the applicable compliance date | submit a request for extension of compliance no later than 120 days before the compliance date, as specified in §§63.9(c) and 63.6(i)(4). |
6. are subject to special requirements as specified in §63.6(b)(3) and (4) | notify the Administrator of your compliance obligations no later than the initial notification dates established in §63.9(b) for new sources not subject to the special provisions, as specified in §63.9(d). |
7. are required to conduct visible emission observations to determine the compliance of flares as specified in §63.11(b)(4) | notify the Administrator of the anticipated date for conducting the observations specified in §63.6(h)(5), as specified in §§63.6(h)(4) and 63.9(f). |
8. are required to conduct a performance test or other initial compliance demonstration as specified in Table 3 to this subpart | a. submit a Notification of Compliance Status Report, as specified in §63.9(h); and b. submit the Notification of Compliance Status Report, including the performance test, CEMS performance evaluation, and any other initial compliance demonstration results within 240 calendar days following the compliance date specified in §63.5495. |
9. comply with the equipment leak requirements of subpart H of this part for existing or new cellulose ether affected sources | comply with the notification requirements specified in §63.182(a)(1) and (2), (b), and (c)(1) through (3) for equipment leaks, with the Notification of Compliance Status Reports required in subpart H included in the Notification of Compliance Status Report required in this subpart. |
10. comply with the equipment leak requirements of subpart UU of this part for existing or new cellulose ether affected sources | comply with the notification requirements specified in §63.1039(a) for equipment leaks, with the Notification Compliance Status Reports required in subpart UU of this part included in the Notification of Compliance Status Report required in this subpart. |
11. comply with the wastewater requirements of subparts F and G of this part for existing or new cellulose ether affected sources | comply with the notification requirements specified in §§63.146(a) and (b), 63.151, and 63.152(a)(1) through (3) and (b)(1) through (5) for wastewater, with the Notification of Compliance Status Reports required in subpart G of this part included in the Notification of Compliance Status Report required in this subpart. |