As stated in §63.8480, you must submit each notification that applies to you according to the following table:

Open Table
If you .  .  . You must .  .  . No later than .  .  . As specified in .  .  .
1. Start up your affected source before December 28, 2015 Submit an Initial Notification June 22, 2016 §63.9(b)(2).
2. Start up your new or reconstructed affected source on or after December 28, 2015 Submit an Initial Notification 120 calendar days after you become subject to this subpart §63.9(b)(2).
3. Are required to conduct a performance test Submit a notification of intent to conduct a performance test 60 calendar days before the performance test is scheduled to begin §63.7(b)(1).
4. Are required to conduct a compliance demonstration that includes a performance test according to the requirements in Table 4 to this subpart Submit a Notification of Compliance Status, including the performance test results 60 calendar days following the completion of the performance test, by the close of business §63.9(h) and §63.10(d)(2).
5. Are required to conduct a compliance demonstration required in Table 5 to this subpart that does not include a performance test (i.e., compliance demonstrations for the work practice standards) Submit a Notification of Compliance Status 30 calendar days following the completion of the compliance demonstrations, by the close of business §63.9(h).
6. Request to use the routine control device maintenance alternative standard according to §63.8420(d) Submit your request 120 calendar days before the compliance date specified in §63.8395