47 CFR § 1.1312
[Amendment] Facilities for which no preconstruction authorization is required
February 16, 2021
* * * * *
(b) If a facility covered by paragraph (a) of this section may have a significant environmental impact, the information required by §1.1311 shall be submitted electronically by the licensee or applicant and ruled on by the Commission, and environmental processing (if invoked) shall be completed, see §1.1308, prior to the initiation of construction of the facility.
* * * * *