StacksVerified U.S. regulatory reference

42 U.S.C. § 16441

Verified against govinfo.gov as of June 20, 2026View official text on govinfo.gov
The Commission may approve a participant funding plan that allocates costs related to transmission upgrades or new generator interconnection, without regard to whether an applicant is a member of a Commission-approved Transmission Organization, if the plan results in rates that—
  1. (1)are just and reasonable;
  2. (2)are not unduly discriminatory or preferential; and
  3. (3)are otherwise consistent with sections 824d and 824e of title 16.