42 U.S.C. § 4336f
Verified against govinfo.gov as of June 20, 2026View official text on govinfo.gov ↗
- (a)
- (1)A project sponsor that intends to pay a fee under this section for the preparation, or supervision of the preparation, of an environmental assessment or environmental impact statement for a project shall submit to the Council—
- (2)Not later than 15 days after the date on which the Council receives information described in paragraph (1) from a project sponsor, the Council shall provide to the project sponsor notice of the amount of the fee to be paid under this section, as determined under subsection (b).
- (3)A project sponsor may pay a fee under this section after receipt of the notice described in paragraph (2).
- (4)Notwithstanding section 4336a(g)(1) of this title—
- (A)an environmental assessment for which a fee is paid under this section shall be completed not later than 180 days after the date on which the fee is paid; and
- (B)an environmental impact statement for which a fee is paid under this section shall be completed not later than 1 year after the date of publication of the notice of intent to prepare the environmental impact statement.
- (b)The amount of a fee under this section shall be—
- (1)125 percent of the anticipated costs to prepare the environmental assessment or environmental impact statement; and
- (2)in the case of an environmental assessment or environmental impact statement to be prepared in whole or in part by a project sponsor under section 4336a(f) of this title, 125 percent of the anticipated costs to supervise preparation of, and, as applicable, prepare, the environmental assessment or environmental impact statement.