42 U.S.C. § 4370m–6 — Litigation, judicial review, and savings provision
Verified against govinfo.gov as of June 20, 2026View official text on govinfo.gov ↗
- (a)Limitations on claims
- (1)In generalNotwithstanding any other provision of law, a claim arising under Federal law seeking judicial review of any authorization issued by a Federal agency for a covered project shall be barred unless—
- (A)the claim is filed not later than 2 years after the date of publication in the Federal Register of notice of final agency action on the authorization, unless a shorter time is specified in the Federal law under which judicial review is allowed; and
- (B)in the case of an action pertaining to an environmental review conducted under NEPA—
- (i)the claim is filed by a party that submitted a comment during the environmental review; and
- (ii)any commenter filed a sufficiently detailed comment so as to put the lead agency on notice of the issue on which the party seeks judicial review, or the lead agency did not provide a reasonable opportunity for such a comment on that issue.
- (2)New information
- (A)In generalThe head of a lead agency or participating agency shall consider new information received after the close of a comment period if the information satisfies the requirements under regulations implementing NEPA.
- (B)Separate actionIf Federal law requires the preparation of a supplemental environmental impact statement or other supplemental environmental document, the preparation of such document shall be considered a separate final agency action and the deadline for filing a claim for judicial review of the agency action shall be 2 years after the date on which a notice announcing the final agency action is published in the Federal Register, unless a shorter time is specified in the Federal law under which judicial review is allowed.
- (3)Rule of constructionNothing in this subsection creates a right to judicial review or places any limit on filing a claim that a person has violated the terms of an authorization.
- (1)In generalNotwithstanding any other provision of law, a claim arising under Federal law seeking judicial review of any authorization issued by a Federal agency for a covered project shall be barred unless—
- (b)Preliminary injunctive reliefIn addition to considering any other applicable equitable factors, in any action seeking a temporary restraining order or preliminary injunction against an agency or a project sponsor in connection with review or authorization of a covered project, the court shall—
- (c)Judicial reviewExcept as provided in subsection (a), nothing in this subchapter affects the reviewability of any final Federal agency action in a court of competent jurisdiction.
- (d)Savings clauseNothing in this subchapter—
- (e)LimitationsNothing in this subchapter preempts, limits, or interferes with—
- (1)any practice of seeking, considering, or responding to public comment; or
- (2)any power, jurisdiction, responsibility, or authority that a Federal, State, or local governmental agency, metropolitan planning organization, Indian tribe, or project sponsor has with respect to carrying out a project or any other provisions of law applicable to any project, plan, or program.