42 U.S.C. § 7274
Verified against govinfo.gov as of June 20, 2026View official text on govinfo.gov ↗
- (1)The Secretary may not proceed with the preparation of an environmental impact statement relating to the construction or operation of a defense facility of the Department of Energy if the estimated cost of preparing such statement exceeds $250,000 unless—
- (A)the Secretary has notified the Committees on Armed Services of the Senate and the House of Representatives of his intent to prepare such statement and a period of thirty days has expired after the date on which such notice was received by such committees; or
- (B)the Secretary has received from each such committee, before the expiration of such thirty-day period, a written notice that the committee agrees with the decision of the Secretary regarding the preparation of such statement.
- (2)The provisions of paragraph (1) shall not apply in the case of any environmental impact statement on which the Secretary began preparation before December 4, 1981.