This section applies to smelters which are required to submit a SIP Compliance Schedule as discussed below.
  1. (a)Each SIP Compliance Schedule required by § 57.201(d) (2) and (3) must contain the following elements:
    1. (1)Description of the overall design of the SO2 control system(s) to be installed;
    2. (2)Descriptions of specific process hardware to be used in achieving compliance with the SIP emission limitation including gas capacity values;
    3. (3)The date by which contracts will be let or purchase orders issued to accomplish any necessary performance improvements;
    4. (4)The date for initiating on-site construction or installation of necessary equipment;
    5. (5)The date by which on-site construction or installation of equipment is to be completed;
    6. (6)The date for achievement of final compliance with SIP emission limitations; and
    7. (7)Any other measures necessary to assure compliance with all SIP requirements as expeditiously as practicable.
  2. (b)Operations of SCS. Smelters to which § 57.705 is applicable must comply with all elements of § 57.703.