Prior to approval by an independent laboratory each system must:
- (a)Satisfy the test method of MSC/Circ. 848 as amended by MSC.1/Circ. 1267 (both incorporated by reference, see § 162.161-2), except that:
- (b)Satisfy the following test requirements as indicated in UL 2166 (incorporated by reference, see § 162.161-2) for halocarbon systems or UL 2127 for inert gas systems (incorporated by reference, see § 162.161-2):
- (1)Nozzle distribution;
- (2)Flow calculation method verification to determine that the manufacturer's calculation method accurately predicts the discharge time, nozzle pressure, and distribution of the extinguishing agent;
- (3)Salt spray corrosion resistance for marine-type systems;
- (4)Vibration resistance of installed components for marine-type systems; and
- (5)Any additional tests contained in UL 2166 for halocarbon systems or UL 2127 for inert gas systems, as required for listing by the independent laboratory.
- (c)Equivalent length of installed components must be identified and included in the test report in accordance with UL 2166 (incorporated by reference, see § 162.161-2) for halocarbon systems or UL 2127 (incorporated by reference, see § 162.161-2) for inert gas systems.