46 CFR §58.30-50
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)All fluid power and control systems installed on a vessel, except those listed in § 58.30-1(a), must meet the following requirements:
- (1)Diagrams of the system providing the information required by § 58.30-40(a)(1) through (4) must be submitted. These are not approved but are needed for records and for evaluation of the system in accordance with § 58.30-1(a)(14).
- (2)The hydraulic fluid used in the system must comply with § 58.30-10.
- (3)The installed system must be tested in accordance with § 58.30-35(c)(2).
- (4)All pneumatic cylinders must comply with § 58.30-30.
- (5)Additional plans may be required for “fail-safe” equipment and for cargo hatch systems with alternate means of operation.
- (b)[Reserved]