48 CFR §209.570-2
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)Except as provided in paragraph (b) of this section, 10 U.S.C. 4292 prohibits any entity performing lead system integrator functions in the acquisition of a major system by DoD from having any direct financial interest in the development or construction of any individual system or element of any system of systems.
- (b)The prohibition in paragraph (a) of this subsection does not apply if—
- (c)In accordance with section 802 of the National Defense Authorization Act for Fiscal Year 2008 (Pub. L. 110-181; 10 U.S.C. 4292 note), DoD may award a new contract for lead system integrator functions in the acquisition of a major system only if—
- (1)The major system has not yet proceeded beyond low-rate initial production; or
- (2)The Secretary of Defense determines in writing that it would not be practicable to carry out the acquisition without continuing to use a contractor to perform lead system integrator functions and that doing so is in the best interest of DoD. The authority to make this determination may not be delegated below the level of the Under Secretary of Defense for Acquisition and Sustainment. Also, see 209.570-3(b).
- (d)Effective October 1, 2010, DoD is prohibited from awarding a new contract for lead system integrator functions in the acquisition of a major system to any entity that was not performing lead system integrator functions in the acquisition of the major system prior to January 28, 2008.