Part 29 — Land Use Management
Subpart A — General Rules
Subpart B — Rights-of-Way General Regulations
- § 29.10— Definitions.
- § 29.11— Purpose and scope.
- § 29.12— Preexisting uses.
- § 29.13— Compatibility-determination requirement.
- § 29.14— Preapplication meeting.
- § 29.15— General application procedures.
- § 29.16— Right-of-way permit application.
- § 29.17— Survey plat and legal description.
- § 29.18— Reimbursement of costs.
- § 29.19— Nature of interest granted.
- § 29.20— Terms and conditions.
- § 29.21— Construction.
- § 29.22— Disposal, transfer, or termination of interest.
- § 29.23— Required payment for use and occupancy of National Wildlife Refuge System land.
- § 29.24— Electric power transmission line rights-of-way.
- § 29.25— Rights-of-way for pipelines for the transportation of oil, natural gas, synthetic liquid, or gaseous fuels, or any refined product produced from these substances.
- § 29.26— Hearing and appeals procedures.
- § 29.27— Severability.
Subpart C — Mineral Operations
Subpart D — Management of Non-Federal Oil and Gas Rights
- § 29.40— What are the purpose and scope of the regulations in this subpart?
- § 29.41— When does this subpart apply to me?
- § 29.42— What authorization do I need to conduct operations?
- § 29.43— If I am already operating under Service authorization, what do I need to do?
- § 29.44— If I am operating without prior Service authorization, what do I need to do?
- § 29.50— What do the terms used in this subpart mean?
- § 29.60— Do I need an operations permit for my pre-existing operation?
- § 29.61— What information must I provide to the Service?
- § 29.62— What if I intend to conduct new operations or modify my pre-existing operations?
- § 29.63— What plugging and reclamation requirements apply to my pre-existing operations?
- § 29.64— What other provisions apply to my operations?
- § 29.70— When do I need a temporary access permit?
- § 29.71— How do I apply for a temporary access permit?
- § 29.72— When will the Service grant a temporary access permit?
- § 29.73— How much time will I have to conduct my reconnaissance surveys?
- § 29.80— Do I need a permit for accessing oil and gas rights from a non-Federal location?
- § 29.90— Who must apply for an operations permit?
- § 29.91— What should I do before filing an application?
- § 29.92— May I use previously submitted information?
- § 29.93— Do I need to submit information for all possible future operations?
- § 29.94— What information must be included in all applications?
- § 29.95— What additional information must be included if I am proposing geophysical exploration?
- § 29.96— What additional information must be included if I am proposing drilling operations?
- § 29.97— What additional information must be included if I am proposing production operations?
- § 29.100— How will the Service process my application?
- § 29.101— How will the Service conduct an initial review?
- § 29.102— How will the Service conduct a formal review?
- § 29.103— What standards must be met to approve my application?
- § 29.104— What actions may the Service take on my operations permit application?
- § 29.110— What are the purposes of the Service's operating standards?
- § 29.111— What general facility design and management standards must I meet?
- § 29.112— What fish and wildlife protection standards must I meet?
- § 29.113— What hydrologic standards must I meet?
- § 29.114— What safety standards must I meet?
- § 29.115— What lighting and visual standards must I meet?
- § 29.116— What noise reduction standards must I meet?
- § 29.117— What reclamation and protection standards must I meet?
- § 29.118— What additional operating standards apply to geophysical operations?
- § 29.119— What additional operating standards apply to drilling and production operations?
- § 29.120— What terms and conditions apply to all operators?
- § 29.121— What monitoring and reporting is required for all operators?
- § 29.122— For how long is my operations permit valid?
- § 29.140— May I cross Federal property to reach the boundary of my oil and gas right?
- § 29.141— Will the Service charge me a fee for access?
- § 29.142— Will I be charged a fee for emergency access to my operations?
- § 29.150— When do I have to provide financial assurance to the Service?
- § 29.151— How does the Service establish the amount of financial assurance?
- § 29.152— Will the Service adjust the amount required for my financial assurance?
- § 29.153— When will the Service release my financial assurance?
- § 29.154— Under what circumstances will I forfeit my financial assurance?
- § 29.160— Can I modify operations under an approved permit?
- § 29.170— What are my responsibilities if I transfer my right to operate?
- § 29.171— What must I do if operations are transferred to me?
- § 29.180— When must I plug my well?
- § 29.181— Can I get an extension to the well plugging requirement?
- § 29.190— What acts are prohibited under this subpart?
- § 29.191— What enforcement actions can the Service take?
- § 29.192— How do violations affect my ability to obtain a permit?
- § 29.200— Can I, as operator, appeal Service decisions?
- § 29.210— How can the public learn about oil and gas activities on refuge lands?
- § 29.220— Has the Office of Management and Budget approved the collection of information?